![]() |
![]() |
|||
Pat Quinn, Governor |
||||
|
Community Relations - Fact SheetsCentralia Environmental Services, Inc. LandfillFact Sheet #2
|
| What is the scope of the current work to be done at the site? | Bodine Environmental Services, the contractor for the State of Illinois, will install a new, protective clay cap on the landfill disposal area (approximately 15 acres) and stabilize an existing wall of exposed refuse. The work that the State of Illinois has contracted includes:
|
| Why is the repair work needed? | Current conditions at the site - insufficient cover material, erosion areas, exposed refuse, and an unstable steep slope - will continue to get worse over time. |
| What is the make-up of the existing cap? | The current cap material consists of a loose, gravel-type material of varying thickness that is insufficient to support proper vegetation. The addition of the 18" of clay and 12" of topsoil will allow for the shedding of water from the landfill and will promote a good ground cover of native grasses. The additional material will be taken from a "borrow" area on the site. |
| How will the new cap be protective? | The new cap will contain the waste material and cause rainwater to flow off the landfill rather than into it, thereby minimizing the production of leachate (rainwater that has contacted waste material). Consequently, this is protective to humans who maintain the site and to the environment. |
| When will the work begin? | The reshaping (moving around existing soils and trash) will begin in August 2001 and will take approximately two weeks. Then begins the process of hauling dirt and compacting it to create the cap. The last step is to apply seed for the ground cover. |
| How long will the work take? | The construction project should take approximately 125 days (weather permitting). The Illinois EPA contractor expects to be finished with the cap and begin seeding the topsoil by late fall 2001. |
| Will the general public be able to use the landfill once it has vegetation on it? | Illinois EPA recommends no public uses of the landfill. Activities such as three-wheeling, motorcycle riding and hiking could damage the cap, causing it to erode. Damage by human activity could allow more water to run through the landfill and produce leachate, which could pollute Webster Creek. |
| How much will the corrective action cost the state? | The total cost of constructing the final cap is estimated to be $1.5 million. |
Public use of this site should be eliminated. Heavy equipment and major construction work scheduled for the site are inherently dangerous. The Illinois EPA is aware of evidence of four-wheeling, motorcycle riding and other types of trespassing that have occurred at the site in the past. There is also evidence of illegal dumping at the site.
| Carol
Fuller Community Relations Coord Illinois EPA (217) 524-8807 |
Ann Cross, Project
Manager Illinois EPA, Bureau of Land, State Sites Illinois EPA (217) 524-1654 |
Maggie Carson, Public Information Officer Bureau of Land Illinois EPA (217) 557-8138 |
Community Relations |
| About Community Relations |
| Staff Directory |
| Fact Sheets |
| Copyright © 1996-2011 Illinois EPA | Agency Site Map | Privacy Information | Kids Privacy | Web Accessibility | Agency Webmaster |