|
|
New Jersey Zinc/Mobil Chemical Superfund Site
Progress Report
July 2006
DePue, Illinois
This fact sheet is a project update about work accomplished at the New Jersey
Zinc/Mobil Chemical Superfund site (“Site”) in the Village of DePue
during the year 2005, and projected activities for 2006. Significant progress was
made in several of the Operable Units (OUs), or areas of concern associated with
the Site. In 1995, the State of Illinois and the potentially responsible parties
(PRPs)1 entered into an Interim Consent Order to conduct
Remedial Investigation/Feasibility Study activities, including investigation and
remediation of the following Operable Units: OU1, South Ditch Sediment; OU2, Phosphogypsum
Stack; OU3, Former Plant Site; OU4, Off-Site Soil; and OU5, DePue Lake and Floodplain.
During 2005, the following activities were completed by the PRPs with oversight
by the Illinois EPA.
OU1, South Ditch Sediment
- A Remedial Design Work Plan was completed by the DePue Group and approved
by Illinois EPA in January 2005.
- Excavation of 4,026 cubic yards of South Ditch sediment, with treatment and
dewatering of the sediment and placement in a Corrective Action Management Unit
constructed on the former plant site, was completed in November 2005.
- The South Ditch work area was restored in November 2005.
OU2, Phosphogypsum Stack
- The DePue Group prepared Design and Construction Drawings and Bid Sheets for
Closure of the fourth and final pond in the Southeast Quadrant of the Phosphogypsum
Stack.
- The Center-Pivot Spray Irrigation System pumped 47 million gallons from the
Clear Water Pond.
- Phosphogypsum sediments and natural soils were excavated and hauled from the
Return Water Channel area and were incorporated into the phosphogypsum stack.
Natural soils were used as final cover for the stack and to rough-grade the 6.4-acre
Return Water Channel area. A free water surface treatment wetland is proposed
to be constructed in the Return Water Channel of the DePue Phosphogypsum Stack
Clearwater Pond.
- The DePue Group began Treatment Wetland Design and submitted a Phosphogypsum
Stack Vegetation Management Plan to Illinois EPA for review and approval.
- As of December 2005, the draft Phase II Hydrogeologic Investigation report
and Phase III Work Plan are considered 99% complete.
- Grading of the Southeast Quadrant was finished by November, a final soil cover
was applied, and the area was seeded with winter wheat. Erosion control measures
were applied to the side slopes of the Return Water Channel area, including seeding
with winter wheat and placement of erosion control matting along the side slopes
of the proposed treatment wetland area.
OU3, Former Plant Site
The DePue Group constructed a Corrective Action Management Unit on the former
plant site as a repository for the unnatural sediment removed from the South Ditch.
Interim Water Treatment Plant Operations: During 2005, 6,179,626 gallons of groundwater
and surface water were treated, with 101,901 pounds of zinc, 7,910 pounds of manganese,
and 5,558 pounds of copper removed. Prior to construction and operation of the
Interim Water Treatment Plant in 1997, these metals would have been discharged
into DePue Lake.
The Illinois EPA approved placement of sludge from the Interim Water Treatment
Plant into the Corrective Action Management Unit during the South Ditch work. A
large portion of the solids generated by the Interim Water Treatment Plant during
the South Ditch work came from the South Ditch activity.
A Revised Phase I Remedial Investigation Report and a Phase II Remedial Investigation
Work Plan were being prepared by the DePue Group.
OU4, Off-Site Soil
The results of historical soil sampling by the Illinois Department of Public
Health indicated that elevated levels of metals may exist in residential and non-residential
soils around the DePue Site. Given the existing data, additional investigations
were conducted in the village by the DePue Group to determine the nature and extent
of potential off-site soil impacts; to determine whether waste from the plant site
had been used for fill or other purposes in residential yards or other off-site
properties; and to begin collection of information for a human health and ecological
risk assessment.
- The DePue Group submitted a revised Off-Site Soils Phase I Remedial Investigation
Work Plan and supporting documents, including a Quality Assurance Project Plan,
Field Sampling Plan, and Health and Safety Plan. These documents were approved
by Illinois EPA in May 2005.
- A public availability session was held by Illinois EPA, interviews of village
residents were conducted, and first-round sampling and assessment of the 17 properties
of specific interest from past Illinois Department of Public Health sampling
was completed.
- A comprehensive village-wide walking tour was conducted by the DePue Group
and the Illinois EPA to locate visually identifiable materials historically taken
from the former plant site and used as fill within the DePue area.
- In October, the results of the sampling and assessment were submitted to the
Illinois EPA by the DePue Group in an Off-Site Soil Removal Action Limit Assessment
Report. The Removal Action Assessment has found significantly lower metal concentrations
than Illinois Department of Public Health, and no immediate health threats.
OU5, DePue Lake and Floodplain
The DePue Lake Remedial Investigation Work Plan, including an Ecological and Human
Health Risk Assessment Work Plan, a Quality Assurance Project Plan, Field Sampling
Plan, and Health and Safety Plan, was submitted to the Illinois EPA in February
2005. As of December 2005, the DePue Group has continued to work with Illinois
EPA on a response to comments and preparation of Work Plan revisions.
Projections for 2006
During 2006, a significant number of activities are planned for each of the operable
units at the New Jersey Zinc/Mobil Chemical site.
- Fieldwork for the DePue Lake Remedial Investigation will be initiated, including
sampling and analysis of sediment to depths up to 15 feet below current lake
bottom, surface water, living plants, animals, and water species, mapping of
spring water flows into the lake, performance of sedimentation studies, and floodplain
and background lake investigations.
- The initial Removal Action Assessment has been completed and the Off-Site
Soils Remedial Investigation will be started. As part of the Off-Site Remedial
Investigation, a limited number of properties investigated as part of the Removal
Action Limit Assessment may be further examined.
- The DePue Group expects to submit the Revised Phase I Report for the Former
Plant Site Remedial Investigation to Illinois EPA in May 2006, and the Phase
II Remedial Investigation Work Plan in June 2006. Phase II Remedial Investigation
activities on the Plant Site are anticipated to begin later in 2006.
- The Phosphogypsum Stack will be revegetated, with a large-scale pilot test
of native prairie grass establishment.
- Construction of the Phosphogypsum Stack Treatment Wetland is scheduled for
completion.
Although much was accomplished in 2005, the Illinois EPA and the DePue Group
are committed to progressing with the investigations and environmental studies
needed in each of the Operable Units of the New Jersey Zinc/Mobil Chemical site.
With the schedule planned for 2006, and the continued cooperation of other state
agencies and the Village of DePue, further progress is anticipated during the upcoming
year.
|
|