Western Lion and Service Disposal #1 Landfill Sites
Fact Sheet #2
May 2000
Charleston, Illinois
Background
After a history of environmental violations at the Western Lion and Service
Disposal #1 Landfill sites, the Illinois EPA learned in May 1994 that the owner/operator
of the site had begun excavating a trench in an area of buried waste without
a permit. A temporary order from the Attorney General's Office required all
operations to stop by January 20, 1996. During an inspection by Illinois EPA
in June 1997, field personnel discovered that the open trench had filled with
35-40 feet of leachate (rainwater that has traveled through the landfill and
contacted waste). This leachate pit occasionally overtopped its banks and flowed
into the nearby Riley Creek, which is a Class "A" Stream.
The State of Illinois appropriated Illinois FIRST funds to correct the situation
at the landfill, once the site owner declared bankruptcy. During the summer
and fall of 1999, the State of Illinois contracted work to dewater the pit of
leachate and fill it with construction debris and other clean fill material.
More than two million gallons of leachate were hauled to Mattoon's publicly-owned
wastewater treatment plant for treatment. The next step is to make corrections
to the existing inadequate landfill cap on both sites.
What is the scope of the current work to be done at the site?
Bodine Environmental Services, the contractor for the State of Illinois, will
install a new, protective clay cap on the landfill sites (a total of 66 acres).
The work that the State of Illinois has contracted includes:
- Reshaping the surface grade on the landfills to improve the slopes for
proper drainage;
- Installing a landfill cap consisting of two feet of com- pacted clay, two
feet of uncompacted clay and six inches of top soil (seeded with various prairie
plants);
- Installing a fence around the entire site.
Under what authority is the State of Illinois contracting the work?
Section 300.430 (a)(iii)(B) of the National Contingency Plan (NCP) contains
the expectation that engineering controls, such as containment, will be used
for waste that poses a relatively low long-term threat or where removal or treatment
is impractical. At municipal landfills, the up-front knowledge that the source
area will be contained facilitates such early actions as installation of a landfill
cap or a groundwater containment system as a remedy for leachate production
that may contaminate groundwater.
How will this cap be protective?
Because the cap will cause rainwater to flow off the landfill rather than into
the landfill, the production of leachate from the landfill should stop. Consequently,
this is protective to both humans who enter the site (from contacting leachate
material) and Riley Creek, a Class "A" stream that runs through the site. This
is also consistent with the Illinois EPA Non-degradation Policy which grants
special protection from new or increased loading of pollutants to Class "A"
streams.
Class A Stream - This is a Biological Stream Characterization
which indicates a "Unique Aquatic Resource" compar- able to the best situations
without human disturbance.
What is the cap made of?
As stated in the first response, there will be a total of four feet of clay
(half compacted, half not compacted) and six inches of topsoil. By installing
the layers in a specific sequence and establishing a good ground-cover layer
of prairie plants, the landfill will be able to shed water much more efficiently
than with the loose gravel material and sparse vegetation that is currently
in place.
When will the work begin?
The reshaping (pushing around existing soils and trash) will begin during June
2000, and will take approximately two weeks. Then begins the process of hauling
dirt and compac- ting it to create the cap. The last step is to apply seed for
ground cover.
How long will the work take?
The construction project should take 180 days. The Illinois EPA contractor
expects to be finished with the cap and begin seeding the top soil with prairie
plants by late fall 2000.
Will the general public be able to use the landfill once it has cover?
Illinois EPA recommends no public uses of the landfill. Activities such as
three-wheeling, motor cycle riding and hiking could damage the cap, causing
it to erode. Damage by human activity may allow more water to run through the
landfill and produce leachate, which could continue to pollute Riley Creek.
In addition, potentially dangerous methane gases will continue to emit from
vents and flares for some time.
How much will the corrective action cost the state?
The cost of dewatering the leachate pit last year amounted to $350,000. The
total cost of the final cap is estimated to be $3.5 million, in addition to
the previous work.
For Additional Information
Carol Fuller
Community Relations Coord.
Illinois EPA
1021 N. Grand Ave. E.
Box 19276
Springfield, Illinois 62794-9276 217/524-8807 fax 785-7725 |
Jody Kershaw
Project Manager
Illinois EPA,
Bureau of Land
1021 N. Grand Ave. E.
Box 19276
Springfield, Illinois 62794-9276
217/785-6871 |
| |
|
Maggie Carson
Public Information Officer
Illinois EPA
Bureau of Land
1021 N. Grand Ave. E.
Box 19276
Springfield, Illinois 62794-9276
217/557-8138 |
|
|